INSP-Final Inspection | 11/10/2016 | 11/10/2016 | 11/10/2016 | P | PASS |
Troy Cobbley
|
|
|
Tested functionality and reporting to panel. Engineered electrical plan sheet fire alarm design (special systems) onsite. Fire Alarm shop drawings need to be turned in by fire alarm contractor indentifying passagway notification, via as-built submittal.
|
INSP-Alarm Testing | 11/9/2016 | 11/9/2016 | 11/9/2016 | P | PART |
Troy Cobbley
|
|
|
Inspection and testing complete in commercial kitchen area of level 1a of GBAD.
|
INSP-Final Inspection | 9/1/2016 | 9/1/2016 | 9/1/2016 | A | PART |
Jim Page
|
|
|
Final fire alarm inspection for level 4 fire of city center side of the building complete, level 4 of the convention center side of fire alarm system will be completed at a later date.
|
INSP-Final Inspection | 8/1/2016 | 8/3/2016 | 8/3/2016 | P | CANC |
Jim Page
|
|
|
Inspection request was for clearwater TI, this inspection request cancelled.
|