INSP-Final Inspection | 11/14/2016 | 11/14/2016 | 11/14/2016 | P | PASS |
Jim Page
|
|
|
Final Fire inspection complete
|
INSP-Final Inspection | 9/1/2016 | 9/1/2016 | 9/1/2016 | A | PART |
Jim Page
|
|
|
Final fire sprinkler inspection for level 4 fire sprinkler system located in city center building complete, convention center side of level 4 will be inspected at a later date.
|
INSP-Sprinkler Rough-in | 8/23/2016 | 8/23/2016 | 8/23/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located on level 4 complete, overhead fire sprinkler piping located on level 4 of the clearwater building approved for cover.
|
INSP-Sprinkler Rough-in | 7/27/2016 | 7/28/2016 | 7/28/2016 | P | PART |
Jim Page
|
|
|
Rough to cover inspection complete for 4th floor south bathrooms, south 4th floor bathrooms approved for cover.
|
INSP-Sprinkler Rough-in | 7/21/2016 | 7/22/2016 | 7/22/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for hardlids located in the restrooms, 4th floor northside complete, hardlids approved for cover.
|
INSP-Conference | 5/9/2016 | 5/10/2016 | 5/10/2016 | P | CANC |
Jim Page
|
|
|
Conference request will be rescheduled due to a doctors appointment per conversation with Richard, conference will be rescheduled for a later date.
|
INSP-Sprinkler Rough-in | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PASS |
Jim Page
|
|
|
Rough in inspection complete, a follow up RTC inspection will need to be scheduled after finish ceilings are complete for cover approval.
|