Permit Information
Permit NumberFIR16-00265
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 777 W MAIN ST
Project NameValley Regional Transit TI
Customer Number 
ePlanReviewYes
Description
[City Center Plaza - Valley Regional Transit]
Connect the existing core fire sprinkler system and install new main lines and branch to supply the entire basement floor of the City Center Plaza. The system is designed for OHII.

Plan Mod #1 – 9/16/2016
Added protection east of column line 4 on FP-2
Add protection to the ramp east of column line 4

(VALLEY REGIONAL TRANSIT – MAIN STREET STATION – CITY CENTER PLAZA BASEMENT) To construct a Multi-Modal Transit Center in the basement of the new City Center Plaza building. The space will include offices, public waiting areas, and bus circulation. The total basement area, not including the bus ramps, is about 45,978 square feet. Work is to include interior nonbearing walls, 2 public multiple fixture restrooms accessible to the disabled, 2 single user employee restrooms accessible to the disabled, interior doors, interior windows, suspended acoustical ceilings, benches, service windows, and finishes. The office, waiting, and restroom areas are conditioned where the bus circulation and platform areas are not condition. A thermal envelope that complies with the energy code is required between conditioned and unconditioned areas. Special Inspection is required for welding. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/10/201610/10/201610/10/2016PPASS
DetailsJim Page
Final fire sprimkler inspection for VRT passed/complete
INSP-Sprinkler Rough-in9/27/20169/29/20169/29/2016PPASS
DetailsJim Page
200 psi hydrostatic test for VRT Dry Systems passed/complete.
INSP-Sprinkler Rough-in9/27/20169/28/20169/28/2016PPASS
DetailsJim Page
24 hour air test for dry systems locared in the VRT section complete. Rough to cover inspection for all overhead fire sprinkler piping located VRT complete, all overhead fire sprinkler piping located in VRT approved for cover.
INSP-Final Inspection9/13/20169/19/20169/19/2016PCANC
DetailsJim Page
No inspection request needed for today per conversation with Mike, phone number ###-####, this inspection request is cancelled.
INSP-Sprinkler Rough-in/Hydro9/13/20169/16/20169/16/2016PPASS
DetailsJim Page
Rough to cover inspection complete for overhead fire sprinkler piping located in VRT, overhead fire sprinkler piping located in VRT approved for cover.
INSP-Sprinkler Rough-in9/14/20169/14/20169/14/2016PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located above soffits in VRT complete, overhead fire sprinkler piping located above soffits in VRT approved for cover.
INSP-Sprinkler Rough-in9/9/20169/12/20169/12/2016APASS
DetailsJim Page
Rough to cover inspection for west side drive through area & the southeast side ramp overhead fire sprinkler piping complete. Overhead fire sprinkler piping located in the west side drive through area & the southeast side ramp approved to cover. Rough to cover inspection for the fire sprinkler piping located above the ceilings in the central waiting/office area for VRT complete, overhead fire sprinkler piping in VRT waiting/office area approved for cover.
INSP-Sprinkler Rough-in8/16/20168/16/20168/16/2016PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located above hardlids in VRT complete, overhead fire sprinkler piping above hardlids in VRT approved for cover.
INSP-Sprinkler Rough-in8/1/20168/2/20168/2/2016APART
DetailsJim Page
Rough to cover inspection complete for heads in soffit by main north stairs, need to verify proper installation for dry pendants in soffit area east of the main stairs.