INSP-Final Inspection | 1/16/2018 | 1/17/2018 | 1/17/2018 | P | PASS |
Jim Page
|
|
|
Final fire sprinkle rinspection for area of work complete.
|
INSP-Final Inspection | 10/9/2017 | 10/9/2017 | 10/9/2017 | A | PART |
Jim Page
|
|
|
Final fire sprinkler inspection complete, permit will remain in issued status until completion of the project.
|
INSP-Sprinkler Rough-in/Hydro | 9/28/2017 | 9/29/2017 | 9/29/2017 | P | PASS |
Jim Page
|
|
|
24 hour air test for both dry systems complete. Trip test for both dry systems complete.
|
INSP-Sprinkler Rough-in/Hydro | 9/27/2017 | 9/28/2017 | 9/28/2017 | P | PART |
Jim Page
|
|
|
Hydrostatic test for level 1 dry system complete. 24 hour air test start at 3:00PM @ 41PSI
|
INSP-Sprinkler Rough-in/Hydro | 9/27/2017 | 9/28/2017 | 9/28/2017 | A | PART |
Jim Page
|
|
|
24 hour air test for level 2 dry system started at 7:15AM @ 40PSI
|
INSP-Sprinkler Rough-in/Hydro | 9/26/2017 | 9/27/2017 | 9/27/2017 | P | PART |
Jim Page
|
|
|
Hydrostatic test for level 2 dry system complete.
|
INSP-Sprinkler Rough-in/Hydro | 9/22/2017 | 9/25/2017 | 9/25/2017 | P | CANC |
Jim Page
|
|
|
Hydrostatic test for dry system will be rescheduled for a later date, test could not be completed before the end of business day.
|
INSP-Sprinkler Rough-in | 8/1/2017 | 8/1/2017 | 8/1/2017 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in above garage drive thru area complete (area just north of elevator lobby) approved for cover.
|
INSP-Sprinkler Rough-in | 7/14/2017 | 7/17/2017 | 7/14/2017 | A | CANC |
Jim Page
|
|
|
Contact will be Leroy Anderson please contact him 30 min prior to Inspection start... RTC - On 1st floor Prkg Garage drive thru area.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|