INSP-Final Inspection | 11/23/2016 | 11/28/2016 | 11/28/2016 | A | PASS |
Katie Marron
|
|
|
System tested satisfactory. Scope of work complete. Permit Finaled
|
INSP-Final Inspection | 11/22/2016 | 11/23/2016 | 11/23/2016 | A | CANC |
Katie Marron
|
|
|
During pretest it was found Bell is wired wrong. Will be rescheduled.
|
INSP-Final Inspection | 11/10/2016 | 11/14/2016 | 11/14/2016 | P | CANC |
Troy Cobbley
|
|
|
Call Anthony before heading out to confirm a time, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 11/9/2016 | 11/10/2016 | 11/10/2016 | P | CANC |
Katie Marron
|
|
|
Please call Anthony before you head out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Final Inspection | 11/2/2016 | 11/4/2016 | 11/4/2016 | P | CANC |
Katie Marron
|
|
|
Call Anthony before you head out, thank you! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in | 9/13/2016 | 9/13/2016 | 9/13/2016 | P | DONE |
Katie Marron
|
|
|
Tenting inspection. At time of inspection, tenting completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 9/6/2016 | 9/6/2016 | 9/6/2016 | P | PASS |
Katie Marron
|
|
|
Hydrostatic re-test passed satisfactorily
|
INSP-Sprinkler Rough-in/Hydro | 9/1/2016 | 9/2/2016 | 9/2/2016 | P | FAIL |
Katie Marron
|
|
|
Roughin completed satisfactory. Hydrostatic test failed.
|
INSP-Sprinkler Rough-in/Hydro | 8/31/2016 | 9/1/2016 | 9/1/2016 | P | FAIL |
Jim Page
|
|
|
Contractor did not have overhead fire protection piping ready for hydrostatic test, hydro will need to be rescheduled for overhead fire sprinkler piping.
|