INSP-Final Inspection | 2/8/2017 | 2/8/2017 | 2/8/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 2/2/2017 | 2/2/2017 | 2/2/2017 | P | PART |
Jim Page
|
|
|
Final inspection for level 6 complete
|
INSP-Final Inspection | 1/13/2017 | 1/13/2017 | 1/13/2017 | A | PART |
Jim Page
|
|
|
Final fire sprinkler inspection for levels 1 through 4 complete. Tamper and flow switch inspections complete for levels 1 through 6.
|
INSP-Sprinkler Rough-in/Hydro | 1/5/2017 | 1/6/2017 | 1/6/2017 | A | PASS |
Troy Cobbley
|
|
|
Hydro test for the 6th floor passed.
|
INSP-Sprinkler Rough-in | 12/23/2016 | 12/27/2016 | 12/27/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in corridors and drop ceilings in rooms on level 6 complete, main corridors and drop ceilings in rooms approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 12/23/2016 | 12/27/2016 | 12/27/2016 | A | PASS |
Jim Page
|
|
|
4th floor and 5th floor hydrostatic test for overhead fire sprinkler piping complete
|
INSP-Final Inspection | 12/16/2016 | 12/16/2016 | 12/16/2016 | P | PART |
Jim Page
|
|
|
Partial final complete for phased occupancy on the overhead fire sprinklers. Items completed are the fire pump room, pump commissioning, east and west standpipes, levels 1, 2 and 3, tampers and flow switches for mentioned area's passed/complete. Remaining area's for overhead fire sprinklers will be inspected at a later date when completed.
|
INSP-Sprinkler Rough-in/Hydro | 12/14/2016 | 12/15/2016 | 12/15/2016 | P | PART |
Jim Page
|
|
|
Hydrostatic test complete for levels 1, 2 and 3 as well as west standpipe.
|
INSP-Sprinkler Rough-in | 12/13/2016 | 12/14/2016 | 12/14/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for pendant heads located in drive through area on level 1 complete, area mentioned approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 12/12/2016 | 12/13/2016 | 12/13/2016 | A | DONE |
Jim Page
|
|
|
Fire pump commissioning complete.
|
INSP-Sprinkler Rough-in | 12/9/2016 | 12/9/2016 | 12/9/2016 | A | PART |
Jim Page
|
|
|
Partial rough to cover complete for level 1 parking area, cover approved from fire pump room to the east wall on level 1.
|
INSP-Sprinkler Rough-in | 12/5/2016 | 12/5/2016 | 12/5/2016 | A | PART |
Jim Page
|
|
|
Cover inspection for pendant heads in garage area complete from east side to column lin 6.5, area in parking garage up to column 6.5 approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 11/14/2016 | 11/15/2016 | 11/15/2016 | A | PART |
Jim Page
|
|
|
Rough to cover inspectio for overhead fire sprinkler piping located above the ceiling grid on level 2 complete, overhead fire sprinkler piping located above ceiling grid on level 2 spproved for cover. Partial tenting inspection for fire sprinkler piping located on level 6 complete, notated city approved drawings areas approved for cover.
|
INSP-Sprinkler Rough-in | 9/22/2016 | 9/23/2016 | 9/23/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located on level 5 complete, overhead fire sprinkler piping located on level 5 approved for cover.
|
INSP-Sprinkler Rough-in | 9/22/2016 | 9/22/2016 | 9/22/2016 | P | CANC |
Troy Cobbley
|
|
|
Per discussion with Adam this is rescheduled for tomorrow morning
|
INSP-Sprinkler Rough-in | 9/9/2016 | 9/9/2016 | 9/9/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for requested area's on level 1 west side complete, notated city approved drawings with pink highlighter area's inspected and approved for cover.
|
INSP-Sprinkler Rough-in | 9/2/2016 | 9/2/2016 | 9/2/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located on level 4 west complete, notated city approved drawings with green highlighter fire sprinkler piping area's that are approved for cover.
|
INSP-Sprinkler Rough-in | 8/24/2016 | 8/25/2016 | 8/25/2016 | A | PASS |
Jim Page
|
|
|
Partial rough to cover inspection complete for overhead fire sprinkler piping on levels 2, 3 and 4. Notated the city approved drawings with green highlighter overhead fire sprinkler piping approved for cover.
|
INSP-Sprinkler Rough-in | 7/27/2016 | 7/28/2016 | 7/28/2016 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping located on level 3 complete, notated the city approved drawings with pink highlighter/red ink area's approved for cover.
|
INSP-Sprinkler Rough-in | 7/13/2016 | 7/13/2016 | 7/13/2016 | P | PART |
Jim Page
|
|
|
Partial rough to cover complete for level 2 overhead fire sprinkler piping, notated the city approved drawings with blue highlighter/red ink, the overhead fire sprinkler piping approved for cover.
|
INSP-Sprinkler Rough-in | 6/24/2016 | 6/27/2016 | 6/27/2016 | A | PART |
Jim Page
|
|
|
Pre-set hangers on level 2 west as well as northwest side approved for cover. Rough to cover inspection complete for level 1 west side overhead fire sprinkler piping, notated city approved drawings with green highlighter & red ink area's approved for cover.
|