INSP-Final Inspection | 9/6/2016 | 9/7/2016 | 9/7/2016 | A | PASS |
Jim Page
|
|
|
Previously noted items have been repaired/addressed, final fire sprinkler inspection passed/complete.
|
INSP-Sprinkler Rough-in/Hydro | 6/13/2016 | 6/13/2016 | 6/13/2016 | P | FAIL |
Troy Cobbley
|
|
|
Resubmit hydraulic calculations to plan review showing the additional eight 3" 90's and pipe routing changes, provide sprinkler coverage under the combustible stairs (not shown on plans) per NFPA 8.15, two of the new branchlines appear to be blocked by 12" beams and 8" z-purlins, provide missing 4-way brace at the old anti-freeze loop location as per plans.
|