Information based on query as of Wednesday, June 19, 2024.
Permit Information
Permit NumberFIR16-00322
StatusFinaled
Name THORPE FIRE SPRINKLER SYSTEMS
Site Address 7472 W SAXTON DR
Project NameKensington Apartments Bldg Q
Customer Number 
ePlanReviewYes
Description
[Kensington Apartments - Building Q]
The fire sprinkler scope of work consists of a NFPA 13R system for a four level apartment building. The
system is supplied by 2” underground through a 2” backflow preventer to 1 ½” riser. There are floor
level control valves in a valve house. The system piping is CPVC except for the standpipes which are
steel.
There are four dry manual 4” standpipes.
The drawings are filed under BLD15-01107 in ePlanReview. The NFPA 13-R fire sprinkler system is
used for occupancy and for story increase. To construct a 36,450 square foot four story apartment
building (9,425 sq. ft. 1st story with four 1.a units and four 2.a units, 9,425 sq. ft. 2nd story with four 1.a
units and four 2.a units, 9,425 sq. ft. 3rd story with four 1.a units and four 2.a units, and 8,175 sq. ft. 4th
story with four 1.a units and four 1.b units). All ground floor units are required to comply as Type B
dwelling units. No elevator is provided in this building. Work is to include concrete footings, concrete
foundations, concrete slabs on grade, wood stud bearing walls, wood stud shear walls, fiberglass
shingles, fiber-cement board siding, manufactured stone veneer, 1-hr dwelling unit separations, .5-hr
minimum fire-resistance-rated corridors with 20-minute smoke- and draft-control doors, exterior exit
stairways fire rated like the corridors, steel stairways with concrete treads, interior nonbearing walls,
millwork, and finishes. Special Inspection is required for soils and for concrete. The roof truss design is
a deferred submittal item. The work is required to comply with the approved drawings, with the plan
review report, and with all applicable codes and ordinances. The fire sprinkler system is required to
comply with NFPA 13-R and the fire alarm system is required to comply with NFPA 72 as regulated by
the Fire Department. Separate fire sprinkler permits and fire alarm permits shall
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/11/20171/11/20171/11/2017PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete.
INSP-Final Inspection12/30/20161/4/20171/4/2017PCANC
DetailsJim Page
Could not test level 2 due to a cut pipe, cut to piping was made after hydrostatic test. Alarm inspection failed due to sync issues on level 4, cannot perform final inspection on fire sprinklers until fire alarm issue is resolved.
INSP-Supply line flush11/29/201611/30/201611/30/2016PDONE
DetailsKatie Marron
supply line flush completed
INSP-Supply line flush11/28/201611/29/201611/29/2016PCANC
DetailsScott Arellano
Suez Water is scheduled to do the flush at 1pm. Please call Jake if there is a conflict. Thank you! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
INSP-Sprinkler Rough-in/Hydro10/12/201610/13/201610/13/2016PCANC
DetailsJim Page
Please call Jake when you are headed out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
INSP-Sprinkler Rough-in9/19/20169/20/20169/20/2016PPASS
DetailsJim Page
Tenting inspection for fire sprinkler piping in attic spaces on level 4 and level 3 complete. Overhead fire sprinkler piping/tenting on level 3 and 4 approved for cover.
INSP-Sprinkler Rough-in/Hydro9/13/20169/14/20169/14/2016APASS
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping located on levels 1, 2, 3 and 4 complete. Rough to cover inspection for overhead fire sprinkler piping complete, levels 1 and 2 approved for cover. Partial cover approved for level 3, fire sprinkler piping located in attic spaces cannot be covered until tenting inspection is complete, all of level 4 not approved for cover until tenting inspection is complete.
INSP-Sprinkler Rough-in/Hydro8/23/20168/24/20168/24/2016PFAIL
DetailsJim Page
Overhead fire sprinkler piping not ready for hydrostatic test, multiple leaks throughout the sprinkler system. Hydrostatic test will need to be rescheduled after repairs are made.
INSP-Sprinkler Rough-in/Hydro8/17/20168/17/20168/17/2016PPASS
DetailsJim Page
200 psi hydrostatic test for standpipe complete
INSP-Supply line flush7/20/20167/21/20167/21/2016APASS
DetailsJim Page
Inspection request was for underground hydrostatic test and underground rough to cover, not a flush. Underground hydrostatic test passed/complete, underground supply approved for cover, flush will be completed at a later date.
INSP-Supply line flush7/20/20167/21/20167/20/2016ACANC
DetailsJim Page
Underground rough inspection. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello