INSP-Final Inspection | 8/11/2017 | 8/14/2017 | 8/14/2017 | A | PASS |
Jim Page
|
|
|
Previously noted items have been repaired, final fire alarm inspection for area of work passed/complete.
|
INSP-Alarm Testing | 11/16/2016 | 11/17/2016 | 11/17/2016 | A | PART |
Troy Cobbley
|
|
|
New notification devices functioned correctly in the new scope of work. The issues is the new devices do not sync with the existing devices outside of the scope of work. I contacted Ron with the Boise Fire Dept and he stated that the new and old devices will need to sync as per code requirements.
|
INSP-Alarm Testing | 10/19/2016 | 10/20/2016 | 10/20/2016 | A | PART |
Troy Cobbley
|
|
|
For a final sign off the new notification devices need to be installed and tested. Per Scott Arellano a 30 temporary for life safety is ok until the new devices are installed and tested.
|
INSP-Alarm Testing | 10/12/2016 | 10/13/2016 | 10/13/2016 | A | DONE |
Troy Cobbley
|
|
|
Need to add smoke detector in the Nurses Station area, need to relocate two other smoke detectors away from air diffusers, one wall mount strobe was non-functional, audio was not temporal but march time, elevator recall was not tested or any of the new smoke detectors in the corridor system. Scott Arellano is ok with a 30 day temporary to allow time for the contractor to correct the audio as long as all other items have been corrected.
|