INSP-Final Inspection | 5/1/2018 | 5/1/2018 | 5/1/2018 | P | PASS |
Jim Page
|
|
|
Final underground supply inspection complete.
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2017 | 12/4/2017 | 12/4/2017 | A | PASS |
Jim Page
|
|
|
Final inspection for fire sprinkler underground supply with buildings 1, 2 and 3 complete.
|
INSP-Supply line flush | 6/9/2017 | 6/9/2017 | 6/9/2017 | A | DONE |
Jim Page
|
|
|
Underground supply flush complete for buildings 1, 2 and 3
|
INSP-Sprinkler Rough-in | 10/11/2016 | 10/11/2016 | 10/11/2016 | P | PASS |
Jim Page
|
|
|
Hydrostatic test for underground supply complete.
|
INSP-Sprinkler Rough-in/Hydro | 10/6/2016 | 10/6/2016 | 10/6/2016 | P | CANC |
Jim Page
|
|
|
Christopher Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/5/2016 | 10/5/2016 | 10/5/2016 | P | PASS |
Jim Page
|
|
|
Underground main supply approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 10/3/2016 | 10/3/2016 | 10/3/2016 | P | PASS |
Jim Page
|
|
|
200 psi hydrostatic test for underground supply complete.
|
INSP-Sprinkler Rough-in | 9/1/2016 | 9/2/2016 | 9/2/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for building 1 fire sprinkler supply underground piping complete, fire sprinkler supply underground piping for building 1 approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 8/11/2016 | 8/12/2016 | 8/12/2016 | A | PASS |
Troy Cobbley
|
|
|
The underground hydro test for Building #2 passed
|
INSP-Sprinkler Rough-in | 8/9/2016 | 8/10/2016 | 8/10/2016 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for underground supply for building 2 complete, building 2 underground supply approved for cover.
|