INSP-Final Inspection | 5/11/2017 | 5/11/2017 | 5/11/2017 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection passed/complete
|
INSP-Alarm Testing | 5/11/2017 | 5/11/2017 | 5/11/2017 | P | DONE |
Jim Page
|
|
|
Alarm testing complete
|
INSP-Final Inspection | 3/23/2017 | 3/24/2017 | 3/24/2017 | A | PART |
Jim Page
|
|
|
Partial final inspection for requested area's for TCO complete (Floors requested for TCO consist of levels 2 and 4) . Initiating devices on levels 1 through 4 have been tested and complete, audio issue has been resolved, A/V's have been inspected for levels 2, 3 and 4, level 1 and parking level will be inspected at a later date. Final fire alarm inspection for levels 2, 3 and 4 passed/complete.
|
INSP-Final Inspection | 3/23/2017 | 3/23/2017 | 3/23/2017 | P | PART |
Jim Page
|
|
|
Partial final inspection for fire alarms complete, all associated devices for fire sprinkler systems tested excluding heat trace monitoring, this will be verified on a later inspection. Audio visual devices inspected on levels 2, 3 and 4, had a noticable audio issue at time of inspection that has apparantly been repaired, will verify audio issue has been repaired on a later inspection.
|