Permit Information
Permit NumberFIR16-00502
StatusFinaled
Name DELTA FIRE SYSTEMS
Site Address 5150 W OVERLAND RD
Project NameIdaho Pizza
Customer Number 
ePlanReviewYes
Description
[Idaho Pizza]
The fire sprinkler scope of work consists of retrofitting existing building with a new fire sprinkler system. The building will be fully sprinkled per NFPA 13 OH 1 & Light Hazard. The building is single level. New 4” underground will supply a new 4” back flow preventer and riser. The system layout is a side feed system with 3” cross main and 1 ¼” branch lines.

[BLD16-NA] – There does not seem to be an associated building permit at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/27/201610/27/201610/27/2016PPASS
DetailsTroy Cobbley
Permit finaled. Forward flush passed
INSP-Final Inspection10/26/201610/26/201610/26/2016PFAIL
DetailsTroy Cobbley
Need to pass the forward flush as discussed.
INSP-Sprinkler Rough-in10/25/201610/25/201610/25/2016PPASS
DetailsTroy Cobbley
Overhead hydro test passed for the new piping added.
INSP-Sprinkler Rough-in/Hydro10/21/201610/21/201610/21/2016PPART
DetailsTroy Cobbley
Overhead hydro test passed. Forward flush failed. It is required to have 7psi but we only got 3psi. Design static pressure was 55psi but 50psi is showing on the bottom guage.
INSP-Supply line flush10/13/201610/13/201610/13/2016PPASS
DetailsTroy Cobbley
Underground flush passed
INSP-Sprinkler Rough-in/Hydro10/6/201610/6/201610/6/2016PPASS
DetailsTroy Cobbley
Underground hydro test passed.
INSP-Sprinkler Rough-in/Hydro10/5/201610/5/201610/5/2016PCANC
DetailsTroy Cobbley
Christopher// the later the better Phone #: ###-####
INSP-Sprinkler Rough-in9/30/201610/3/201610/3/2016PPASS
DetailsTroy Cobbley
The underground supply piping has been modified to meet the min. bury depth. Piping can be buried.
INSP-Sprinkler Rough-in9/29/20169/29/20169/29/2016PFAIL
DetailsTroy Cobbley
Todays inspection was for the underground supply piping. It failed because the dept. of cover does not meet the minum dept of 4'-6". It is running right around 4'-0"
INSP-Sprinkler Rough-in9/19/20169/19/20169/19/2016PPASS
DetailsTroy Cobbley
Rough-in passed. Piping can be covered. Not all of the walls have been installed yet so final pendant head spacing can not be verified yet.
INSP-Sprinkler Rough-in/Hydro9/7/20169/7/20169/7/2016PFAIL
DetailsTroy Cobbley
The installation does not match plans. Resubmittals are required per the review notes due to the safety factor of the hydraulic calculations. I noted numerous pipe routing changes, added fittings and pendant heads spaced at 16' apart. Riser has not been built yet and the underground supply piping has not been installed yet. Rough-in inspection and hydro test stopped due to the issues.