INSP-Final Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Forward flush passed
|
INSP-Final Inspection | 10/26/2016 | 10/26/2016 | 10/26/2016 | P | FAIL |
Troy Cobbley
|
|
|
Need to pass the forward flush as discussed.
|
INSP-Sprinkler Rough-in | 10/25/2016 | 10/25/2016 | 10/25/2016 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed for the new piping added.
|
INSP-Sprinkler Rough-in/Hydro | 10/21/2016 | 10/21/2016 | 10/21/2016 | P | PART |
Troy Cobbley
|
|
|
Overhead hydro test passed. Forward flush failed. It is required to have 7psi but we only got 3psi. Design static pressure was 55psi but 50psi is showing on the bottom guage.
|
INSP-Supply line flush | 10/13/2016 | 10/13/2016 | 10/13/2016 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 10/6/2016 | 10/6/2016 | 10/6/2016 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/5/2016 | 10/5/2016 | 10/5/2016 | P | CANC |
Troy Cobbley
|
|
|
Christopher// the later the better Phone #: ###-####
|
INSP-Sprinkler Rough-in | 9/30/2016 | 10/3/2016 | 10/3/2016 | P | PASS |
Troy Cobbley
|
|
|
The underground supply piping has been modified to meet the min. bury depth. Piping can be buried.
|
INSP-Sprinkler Rough-in | 9/29/2016 | 9/29/2016 | 9/29/2016 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for the underground supply piping. It failed because the dept. of cover does not meet the minum dept of 4'-6". It is running right around 4'-0"
|
INSP-Sprinkler Rough-in | 9/19/2016 | 9/19/2016 | 9/19/2016 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered. Not all of the walls have been installed yet so final pendant head spacing can not be verified yet.
|
INSP-Sprinkler Rough-in/Hydro | 9/7/2016 | 9/7/2016 | 9/7/2016 | P | FAIL |
Troy Cobbley
|
|
|
The installation does not match plans. Resubmittals are required per the review notes due to the safety factor of the hydraulic calculations. I noted numerous pipe routing changes, added fittings and pendant heads spaced at 16' apart. Riser has not been built yet and the underground supply piping has not been installed yet. Rough-in inspection and hydro test stopped due to the issues.
|