Permit Information
Permit NumberFIR16-00508
StatusFinaled
Name THORPE FIRE SPRINKLER SYSTEMS
Site Address 7480 W SAXTON DR
Project NameKENSINGTON APARTMENTS BLDG F
Customer Number 
ePlanReviewYes
Description
[Kensington Apartments - Building F]
The fire sprinkler scope of work consists of a NFPA 13R system for a two level apartment building. The system is supplied by 2” underground through a 2” backflow preventer to 1 ½” riser. There are floor level control valves in a valve house. The system piping is CPVC with extended coverage residential sprinklers.

[BLD15-01123] - The drawings are filed under BLD15-01118 in ePlanReview. The NFPA 13-R fire sprinkler system is used for occupancy. To construct a 10,024 square foot two story apartment and parking garage building (5,032 sq. ft. 1st story with 14 one car garages and one 1.e dwelling unit and 4,992 sq. ft. 2nd story with one 2.h dwelling unit, one 2.f dwelling unit, and three 1.f dwelling units). Two units share an interior stairway, two units share a different interior stairway, and one unit has its own interior stairway. Work is to include concrete footings, concrete foundations, concrete slabs on grade, wood stud bearing walls, wood stud shear walls, fiberglass shingles, fiber-cement board siding, manufactured stone veneer, 1-hr dwelling unit separations, interior stairways, interior nonbearing walls, millwork, and finishes. Special Inspection is required for soils and for concrete. The roof truss design is a deferred submittal item. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13-R as regulated by the Fire Department. Separate fire sprinkler permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/16/201711/16/201711/16/2017PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete.
INSP-Final Inspection11/16/201711/16/201711/16/2017PFAIL
DetailsJim Page
Flow switch leaks when water is being flowed, flow switch will need to be replaced.
INSP-Final Inspection11/14/201711/15/201711/15/2017AFAIL
DetailsJim Page
Upright head in riser room is to far down from the deck. Underground supply is not on so not testing of fire sprinkler associated devices could be tested (Underground valve must be turned on by SUEZ). Riser brace needs to be attached to the floor.
INSP-Sprinkler Rough-in9/25/20179/25/20179/25/2017PPASS
DetailsJim Page
Rough to cover inspection complete, approved for cover.
INSP-Sprinkler Rough-in9/22/20179/22/20179/22/2017AFAIL
DetailsJim Page
Multiple hangers are overspaced in garage area's, garage area's are not approved for cover, any cover material installed that blocks the veiw of fire sprinkler piping/hangers will be removed for follow up inspection.
INSP-Sprinkler Rough-in9/21/20179/22/20179/22/2017APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/tenting on level 2 complete, level 2 approved for cover. Level 1 apartment on east side approved for cover.
INSP-Sprinkler Rough-in/Hydro10/12/201610/13/201610/13/2016PPART
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping complete for levels 1 and 2. Rough to cover inspection for overhead fire sprinkler piping complete, overhead fire sprinkler piping located on level 1 approved for cover, overhead fire sprinkler piping located on level 2 cannot be covered until tenting inspection is complete. The 2nd level has a balcony that is not on the approved drawings, this balcony is on the southside of the building located on the end, balcony needs a dry sidewall install for coverage, sidewall install will be verified during tenting inspection.