Permit Information
Permit NumberFIR16-00511
StatusFinaled
Name THORPE FIRE SPRINKLER SYSTEMS
Site Address 7444 W SAXTON DR
Project NameKENSINGTON APARTMENTS BLDG J
Customer Number 
ePlanReviewYes
Description
[Kensington Apartments - Building J]
The fire sprinkler scope of work consists of a NFPA 13R system for a four level apartment building. The system is supplied by 2” underground through a 2” backflow preventer to (4) 2” risers. There are floor level control valves in a valve house. The system piping is CPVC with extended coverage residential sprinklers.

There is a 4” standpipe with (2) 4” risers. Each standpipe riser has (3) hose valves. The FDC is connected to the standpipe per the fire marshal’s office. Each riser has a supervised sectional control valve.

[BLD15-01126] - The drawings are filed under BLD15-01118 in ePlanReview. The NFPA 13-R fire sprinkler system is used for occupancy and for story increase. To construct a 19,484 square foot four story apartment building (5,189 sq. ft. 1st story with four 2.a units, 5,189 sq. ft. 2nd story with four 2.a units, 5,189 sq. ft. 3rd story with four 2.a units, 3,917 sq. ft. 4th story with four 1.b units). All ground floor units are required to comply as Type B dwelling units. No elevator is provided in this building. Work is to include concrete footings, concrete foundations, concrete slabs on grade, wood stud bearing walls, wood stud shear walls, fiberglass shingles, fiber-cement board siding, manufactured stone veneer, 1-hr dwelling unit separations, .5-hr minimum fire-resistance-rated corridors with 20-minute smoke- and draft-control doors, exterior exit stairways fire rated like the corridor, steel stairways with concrete treads, interior nonbearing walls, millwork, and finishes. Special Inspection is required for soils and for concrete. The roof truss design is a deferred submittal item. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13-R and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/15/20175/16/20175/16/2017APASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Final Inspection5/14/20175/15/20175/15/2017AFAIL
DetailsJim Page
Tamper switches for backflow would not report to panel, all flow switches would not go into alarm with inspectors test.
INSP-Final Inspection5/11/20175/12/20175/12/2017AFAIL
DetailsTroy Cobbley
Not ready for final. Fire alarm contractor was not ready, FDC needs finished, floor needs poured in riser room, riser room needs to be fire caulked, hangers on 2" piping need to be verified as per previous note. Contractor was putting up signage. No actual inspection performed.
INSP-Supply line flush5/4/20175/5/20175/5/2017ADONE
DetailsJim Page
Underground main line flush complete
INSP-Sprinkler Rough-in/Hydro3/9/20173/9/20173/9/2017PPASS
DetailsJim Page
3rd Floor hydrostatic test complete
INSP-Sprinkler Rough-in/Hydro3/7/20173/8/20173/8/2017PPART
DetailsJim Page
Hydro for overhead fire sprinkler piping on levels 1, 2 and 4 complete, level 3 lost pressure, will need to have hydro test completed again for level 3 after repair is made. Rough to cover inspection /tenting inspection complete, all can be covered with exception to the appartment with the 2 inch CPVC suppling the riser from the standpipe/FDC, no hangers were on the 2 inch at time of inspection.
INSP-Supply line flush3/7/20173/8/20173/8/2017PPART
DetailsJim Page
Inspection request is for underground rough/hydro, not supply line flush. Underground rough to cover inspection complete, underground hydro complete.
INSP-Sprinkler Rough-in/Hydro3/6/20173/7/20173/7/2017ACANC
DetailsJim Page
Inspection request cancelled by person onsite, Trevor, inspection request will be rescheduled for a later date.
INSP-Sprinkler Rough-in3/6/20173/7/20173/6/2017ACANC
DetailsJim Page
Tenting inspection. Call Jake when heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
INSP-Sprinkler Rough-in/Hydro2/28/20172/28/20172/28/2017PCANC
DetailsJim Page
Not ready for inspection, this request is cancelled.
INSP-Sprinkler Rough-in/Hydro2/23/20172/24/20172/24/2017APASS
DetailsJim Page
Rough to cover inspection for standpipe complete, approved for cover. Hydrostatic test for standpipe complete.
INSP-Sprinkler Rough-in/Hydro2/9/20172/9/20172/9/2017PFAIL
DetailsJim Page
Standpipe lost pressure during hydro, will need to be re-tested after repair is made.
INSP-Sprinkler Rough-in/Hydro2/8/20172/8/20172/8/2017PCANC
DetailsJim Page
Standpipe rough/hydro inspection cancelled per conversation with point of contact, Jake Phone #: ###-####, inspection request will be scheduled for a later date.
INSP-Sprinkler Rough-in/Hydro1/26/20171/27/20171/27/2017ACANC
DetailsJim Page
Standpipe rough/air test for hydro. Call Jake when heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello