Information based on query as of Thursday, June 27, 2024.
Permit Information
Permit NumberFIR16-00534
StatusFinaled
Name STATEFIRE DC SPECIALTIES
Site Address 5493 E WARM SPRINGS AVE
Project NameRiverstone Middle+High School
Customer Number 
ePlanReviewYes
Description
[Riverstone Middle + High School]
The fire sprinkler scope of work consists of a new wet system to protect a school. There is new 6” underground to a 3” riser with backflow preventer. The system is designed as a dual center feed system with 2 ½” mains and 1 ¼” branch lines. The building has composite wood joists. The joists are to be filled with noncombustible insulation and firestoppped every 160^3 ft. CC2 special application sprinklers are being utilized in the combustible concealed space below the noncombustible insulation.

The underground piping is under permit FIR16-00480

[BLD16-00810] - Permit is to construct a new 7,000 square foot middle / high school. This building is being sprinklered for non-rated corridors and future expansions. Approval contingent upon adhering to the approved plans on file. Work to include: removal of two existing portable classroom buildings, removal of two existing canopies on separate adjacent buildings, construction of poured concrete foundation, construction of new wood frame building, [installation of new nonbearing walls to create five classrooms, two storage rooms, separate sex accessible restrooms, two offices, a hallway, and a small break out classroom], new electrical, new mechanical, new plumbing, and interior finishes in compliance with chapter 8 of the 2012 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/1/201612/2/201612/2/2016APASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Final Inspection11/28/201611/30/201611/30/2016PNR
DetailsKatie Marron
Fire alarm portion not ready. Not prepared for forward flow test.

Tested inspectors test/flow switch and bell function. Checked escutcheons
INSP-Sprinkler Rough-in/Hydro11/28/201611/30/201611/30/2016PPASS
DetailsKatie Marron
Hydrostatic test completed saitsfactory.
INSP-Sprinkler Rough-in11/9/201611/9/201611/9/2016PPASS
DetailsKatie Marron
Completed rough-in of grid ceiling. Ok to cover.
INSP-Sprinkler Rough-in10/24/201610/24/201610/24/2016APART
DetailsJim Page
Rough in inspection for overhead fire sprinkler piping complete, another rough to cover inspection will need to be performed for cover after ceiling grid and finish pendant heads are installed.