INSP-Final Inspection | 12/22/2016 | 12/22/2016 | 12/22/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work for this permit complete, notes for hotel have been added to this permit from past inspection requests due to permit number confusion.
|
INSP-Sprinkler Rough-in | 11/9/2016 | 11/9/2016 | 11/9/2016 | P | CANC |
Katie Marron
|
|
|
Will be rescheduled for tomorrow. Arrived on site but contractor had left already for the day. Adam Phone #: ###-####
|
INSP-Sprinkler Rough-in | 11/7/2016 | 11/7/2016 | 11/7/2016 | P | CANC |
Katie Marron
|
|
|
Contact number provided was a discontinued number. Reschedule and provide correct contact information.
|
INSP-Sprinkler Rough-in | 10/21/2016 | 10/21/2016 | 10/21/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler on level 6 complete, city approved plans are notated with yellow highlighter, overhead fire sprinkler piping on level 6 approved for cover.
|
INSP-Sprinkler Rough-in | 10/12/2016 | 10/12/2016 | 10/12/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located at 3rd level east hallway complete, overhead fire sprinkler located in noted area approved for cover.
|
INSP-Sprinkler Rough-in | 10/7/2016 | 10/7/2016 | 10/7/2016 | P | PASS |
Troy Cobbley
|
|
|
See the second floor plans where I have notated with todays day the corridor system where piping can be covered.
|
INSP-Sprinkler Rough-in | 10/6/2016 | 10/6/2016 | 10/6/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located in the level 2 northeast corridor complete, overhead fire sprinkler piping located in the level 2 northeast corridor approved for cover.
|
INSP-Sprinkler Rough-in | 9/28/2016 | 9/28/2016 | 9/28/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for fire sprinkler piping located above hardlids in restroom and soffits in dining area complete, overhead fire sprinkler piping in noted area's approved for cover.
|