Permit Information
Permit NumberFIR16-00588
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 3575 W OVERLAND RD
Project NameBoise Fire Station #8
Customer Number 
ePlanReviewYes
Description
[Boise Fire Station #8]
The fire sprinkler scope of work consists of protecting a two level fire station per NFPA 13. The system has a 4” backflow preventer with 4” header and 4” floor control valves.

As Built 1/20/2017
Rerouted main(s) on second floor. New hydraulic calculations were provided.
Change sprinklers to upright in stairway on second level.
Rerouted main(s) on the first floor

The underground is under permit FIR16-00477

[BLD16-01092] - Permit to construct a new 11,936 square foot fire station. This building is fire sprinklered for area increase and non-separated uses. This building utilizes enhanced lighting to comply with the 2012 IECC. Scope of work includes: construction of poured concrete foundation, construction of reinforced CMU exterior walls, construction of new steel bar-joist floor – ceiling framing / steel pan deck, [construction of interior nonbearing walls to create: 7 sleeping units, 5 restrooms / bathing rooms, lobby, three offices, work room, turn out room, decon room, maintenance shop, riser room, 3 storage rooms, laundry room, janitors closet, fitness room, kitchen, and dayroom], new elevator, new electrical, new plumbing, new mechanical, new interior / exterior finishes, new accessible doors / hardware, and related site work. This building is fully fire sprinklered for area increase. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/26/20174/27/20174/27/2017APASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection4/26/20174/26/20174/26/2017PCANC
DetailsTroy Cobbley
George, inspection is ready this AM if you can make that work. Phone #: ###-####
INSP-Final Inspection4/24/20174/25/20174/25/2017ACANC
DetailsTroy Cobbley
George Jess is the contact for this inspection. He is requesting a final inspection. Thank you. Phone #: ###-#### Inspection requested via web by Kay Haney
INSP-Final Inspection4/21/20174/24/20174/24/2017PCANC
DetailsTroy Cobbley
Water was not turned on yet. I spoke to George about my previous concerns with lack of protection in the room at the bottom of the brass pole.
INSP-Sprinkler Rough-in/Hydro3/10/20173/13/20173/13/2017PPASS
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping passed/complete
INSP-Sprinkler Rough-in2/13/20172/13/20172/13/2017PPASS
DetailsTroy Cobbley
2nd floor sprinkler piping is okay to cover
INSP-Sprinkler Rough-in1/17/20171/18/20171/18/2017APART
DetailsTroy Cobbley
First floor general rough-in passed with a couple of exceptions which include two additional 90's in both 4" mains close to the riser, missing seismic restraints in the Apparatus Bay and possible required coverage below the brass pole, missing seismic bracing and possible blocked heads in restrooms. The second floor rough-in could not be performed due to pipe routing changes. Plans need to be resubmitted for plan modifications. Additional cover inspections will be required when the sprinkler drops have been cut and located.