INSP-Final Inspection | 7/18/2017 | 7/19/2017 | 7/19/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for this permit passed/complete
|
INSP-Final Inspection | 7/6/2017 | 7/7/2017 | 7/6/2017 | A | CANC |
Jim Page
|
|
|
Called point of contact listed, Paul Phone #: ###-####, Installing contractor did not schedule fire sprinkler inspection, inspection for fire sprinklers will not be perfromed if FIR permit is called in by anyone other than the installing contractor.
|
INSP-Sprinkler Rough-in/Hydro | 6/29/2017 | 6/29/2017 | 6/29/2017 | A | PASS |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping complete
|
INSP-Supply line flush | 5/31/2017 | 6/1/2017 | 6/1/2017 | A | CANC |
Jim Page
|
|
|
Cancelled per point of contact, Paul Phone #: ###-####, will be rescheduled.
|
INSP-Sprinkler Rough-in | 5/25/2017 | 5/25/2017 | 5/25/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/pendant heads located above hardlids complete, approved for cover.
|
INSP-Conference | 5/24/2017 | 5/25/2017 | 5/25/2017 | P | DONE |
Jim Page
|
|
|
Fire conference complete
|
INSP-Sprinkler Rough-in | 4/5/2017 | 4/5/2017 | 4/5/2017 | P | FAIL |
Jim Page
|
|
|
Tenting is not complete, no insulation installed over piping in numerous area's. City approved drawings show a detail with attic space being completely filled with insulation, numerous area's have 6 plus inches of combustible material exposed, insulation needs to fill any and all area's in attic space or upright head protection will be required, refer to note number 8 of fire sprinkler permit review comments for specifics.
|
INSP-Conference | 3/10/2017 | 3/13/2017 | 3/13/2017 | P | PART |
Jim Page
|
|
|
Inspection request was for a rough to cover inspection for an area on level 1 clubhouse, notated city approved drawings with red ink area approved for cover.
|