Permit Information
Permit NumberFIR16-00644
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 351 N MITCHELL ST Unit: 300
Project NameFOOD SAFETY NET SERVICES
Customer Number 
ePlanReviewYes
Description
[Food Safety Net Services]
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration. A new mezzanine is protected by dropping down from the above system.

[BLD16-03242] - New food safety laboratory and offices within an existing 8,475 sq. ft. space with work to include the addition of a 4,843 second story to include offices, training rooms and food testing facilities. This building is fully fire sprinklered for area increase. Any alterations to the sprinkler system will require a separate permit and shall comply with NFPA 13 as regulated by the fire department. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/6/20172/7/20172/7/2017PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro2/2/20172/3/20172/3/2017APASS
DetailsTroy Cobbley
City pressure hydro on the hole system passed.
INSP-Sprinkler Rough-in1/30/20171/31/20171/31/2017APART
DetailsTroy Cobbley
Remaining piping can be covered. High temp heads need to be installed infront of the unit heaters as per table 8.3.2.5(a)
INSP-Sprinkler Rough-in1/20/20171/23/20171/23/2017PPASS
DetailsTroy Cobbley
Second floor rough-in passed. Piping can be covered.
INSP-Sprinkler Rough-in/Hydro1/17/20171/18/20171/18/2017APASS
DetailsTroy Cobbley
Overhead hydro for the under mezzanine piping passed. Previous corrections done except for the seismic bracing in the corridor.
INSP-Sprinkler Rough-in1/16/20171/17/20171/17/2017APASS
DetailsTroy Cobbley
See the city approved plans for locations where sprinkler piping on the first floor is ok to cover. Also see acouple of locations where minor corrections are needed.
INSP-Sprinkler Rough-in11/30/201611/30/201611/30/2016PPASS
DetailsTroy Cobbley
Piping above the hardlid next to the elevator as marked on the plans is ok to cover.