INSP-Final Inspection | 7/11/2019 | 7/11/2019 | 7/11/2019 | A | PASS |
Jim Page
|
|
|
Final inspection for undergorund supply has been completed.
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2019 | 7/11/2019 | 7/11/2019 | P | DONE |
Jim Page
|
|
|
Underground hydrostatic test has been witnessed, no pressure loss was observed.
Clearnce Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2019 | 7/11/2019 | 7/11/2019 | A | CANC |
Jim Page
|
|
|
|
INSP-Supply line flush | 9/26/2017 | 9/27/2017 | 9/27/2017 | P | DONE |
Jim Page
|
|
|
S.W. Riser Underground Flush main line flush complete
|
INSP-Supply line flush | 7/18/2017 | 7/19/2017 | 7/19/2017 | P | DONE |
Jim Page
|
|
|
Underground main line flush for east riser room complete
|
INSP-Supply line flush | 6/26/2017 | 6/27/2017 | 6/27/2017 | P | DONE |
Jim Page
|
|
|
Underground flush for southeast riser room complete.
|
INSP-Supply line flush | 6/26/2017 | 6/26/2017 | 6/26/2017 | P | CANC |
Jim Page
|
|
|
1 pm flush per Micron request. Phone #: ###-#### >> Inspection requested via web by Sheldon Gray Inspection cancelled from web by: Sheldon Gray
|
INSP-Supply line flush | 5/2/2017 | 5/4/2017 | 5/4/2017 | A | PART |
Jim Page
|
|
|
N.W. Underground Flush complete
|
INSP-Sprinkler Rough-in | 3/28/2017 | 3/29/2017 | 3/29/2017 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for south east underground, approved for cover.
|
INSP-Sprinkler Rough-in | 2/24/2017 | 2/24/2017 | 2/24/2017 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for underground supply, notated city approved drawings area's approved for cover.
|
INSP-Sprinkler Rough-in | 2/22/2017 | 2/22/2017 | 2/22/2017 | P | PART |
Jim Page
|
|
|
Partial rough to cover for underground supply complete, notated the city approved drawings with red ink area's approved for cover.
|
INSP-Sprinkler Rough-in | 2/2/2017 | 2/2/2017 | 2/2/2017 | P | PART |
Jim Page
|
|
|
Partial cover approved for Northeast underground, notated city approved drawings area approved for cover.
|