INSP-Final Inspection | 6/19/2017 | 6/21/2017 | 6/21/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Supply line flush | 4/24/2017 | 4/25/2017 | 4/25/2017 | A | PASS |
Troy Cobbley
|
|
|
Inspection was for overhad hydro which passed
|
INSP-Sprinkler Rough-in | 3/3/2017 | 3/6/2017 | 3/6/2017 | A | PASS |
Troy Cobbley
|
|
|
Tenting inspection passed and piping can be covered. Also pendant sprinkler modifications due to soffits in the Kitchen have been completed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 3/2/2017 | 3/3/2017 | 3/3/2017 | P | FAIL |
Troy Cobbley
|
|
|
Upon re-inspection we found that the soffits in the Kitchen area are causing obstruction issues with the pendant sprinklers. We discussed spacing solutions. Modifications should be done by Monday for a re-inspection.
|
INSP-Sprinkler Rough-in | 2/24/2017 | 2/27/2017 | 2/27/2017 | P | PART |
Troy Cobbley
|
|
|
Rough-in passed for the piping located above the ceilings. Tenting inspection passed as well for the second floor piping. Before cover the piping located in the exterior wall and above the ceiling in the riser room will need a tenting inspection.
|