Permit Information
Permit NumberFIR17-00030
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1629 N MOCKBEE PL
Project NameSherman Hollow Lot 2
Customer Number 
ePlanReviewYes
Description
This is a 13D single family 5,744 SQ FT dwelling. It has three levels with 4.9K heads in the heated garage and throughout. It has a combination waterline in and will uses a passive purge system. This project doesn't have a water softener. It will use a 1" water meter.

[BLD16-03871] - WUI Zone A; *This structure is required to have a NFPA 13D fire sprinkler system.* *Special inspections required, see form #310* Permit for the construction of a new 3,541 sq. ft., two story (basement level 245 sq. ft., main level 2900 sq. ft., upper level 396 sq. ft.) single family dwelling with 3 bedrooms, 3 bathrooms, approximately 475 sq. ft. of covered patio/porch and a 1915 sq. ft. attached garage per the approved plans, engineering, ACCA report and any notations. R-1B zoning and setbacks per planning. //leg
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/13/201711/13/201711/13/2017APASS
DetailsJim Page
Final fire sprinkler inspection passed/complete.
INSP-Final Inspection11/9/201711/9/201711/9/2017PCANC
DetailsJim Page
Inspection request cancelled by contractor due to flow switch issues. Inspection request will be rescheduled for later date.
INSP-Final Inspection11/8/201711/9/201711/9/2017ACANC
DetailsJim Page
Coordinated for a PM inspection, this request is cancelled.
INSP-Final Inspection11/7/201711/8/201711/8/2017ACANC
DetailsJim Page
Inspection request scheduled for the wrong day per conversation with point of contact, Ricky Sullivan Phone #: ###-####. This inspection request is cancelled and the correct day has been rescheduled.
INSP-Final Inspection10/16/201710/18/201710/18/2017AFAIL
DetailsJim Page
Fire sprinkler head in middle level east room by stairs needs to be relocated, fire sprinkler head is currently 24 inches off of the center of the ceiling fan. Fire sprinkler head located in the west bathroom will need to be changed to an intermediate temperature head, sprinkler head is closer than 24 inches to heat source. Provide documentation showing that the spray in foam insulation is compatible with CPVC. Sheetrock needs to be installed over the exposed CPVC in the small storage room off of the garage. Irriigation was not installed at time of inspection, need to verify that the irrigation water (Irrigation water is supplied from the domestic feed) supply shuts off when flow switch activates.
INSP-Final Inspection10/16/201710/17/201710/16/2017ACANC
DetailsJim Page
Ricky Sullivan is the contact for this final inspection. He would like late AM or early PM inspection time frame if possible. He would like a two hour notice. Thank you for your time. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in/Hydro8/25/20178/28/20178/28/2017APASS
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping complete. Rough to cover inspection for overhead fire sprinkler piping coplete, approved for cover. Insulation is going to be spray foam type to the bottom of the roof deck, tenting not required. If spray foam comes in contact with CPVC then documentation will be required to verify compatibility of spray foam with CPVC piping.
INSP-Sprinkler Rough-in/Hydro8/23/20178/25/20178/25/2017ACANC
DetailsTroy Cobbley
The fitter and I could not make it to the inspection at the same time. Agreed to re-schedule for monday morning