Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberFIR17-00057
StatusFinaled
Name TRIBAL FIRE SYSTEMS
Site Address 8000 S FEDERAL WAY
Project NameMicron Bldg 51 System 10-8
Customer Number 
ePlanReviewYes
Description
[Micron Building 51 - System LV10-8 - C24074]
The fire sprinkler scope of work consists of providing in duct sprinkler protection for two exhaust ducts.

• The underground is under permit FIR16-00701
• Building drawings are also linked in under permit BLD16-01184 (Steel Superstructure)
• Building drawings are also linked in under permit BLD16-03892 (Exterior and Interior Walls)
• See addendum for graphic scope of work.

Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.

[BLD16-03440] - For completion of work not addressed under permit BLD16-03892. For the construction of a new one story building with a basement for a fabrication and R&D facility to include related site work. The building includes a 149,327 sq. ft. basement, a 164,022 sq. ft. first story and a 33,638 sq. ft. equipment platform. This building is fully fire sprinklered and alarmed for H occupancy. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/7/20198/7/20198/7/2019PPASS
DetailsJim Page
Final fire sprinkler inspection for area of work complete.

Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
INSP-Sprinkler Rough-in/Hydro8/7/20198/7/20198/7/2019PDONE
DetailsJim Page
Hydrostatic test for this system has been witnessed, no pressure loss was observed.
INSP-Sprinkler Rough-in8/7/20198/7/20198/7/2019PPASS
DetailsJim Page
Rough in inspection for this system has been completed.
INSP-Final Inspection7/31/20198/1/20198/1/2019ACANC
DetailsTroy Cobbley
Canceling due to manpower shortage and time constraints. Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
INSP-Final Inspection7/31/20197/31/20197/31/2019PCANC
DetailsJim Page
Rescheduled for 01AUG2019 per conversation with point of contact, this request is cancelled.

Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
INSP-Sprinkler Rough-in/Hydro6/22/20176/23/20176/23/2017APASS
DetailsJim Page
Rough to cover inspection complete, approved for cover. Hydrostatic test for overhead fire sprinkler piping complete.