INSP-Final Inspection | 9/24/2018 | 9/24/2018 | 9/24/2018 | P | PASS |
Jim Page
|
|
|
Final inspection for underground supply complete.
|
INSP-Supply line flush | 11/13/2017 | 11/17/2017 | 11/17/2017 | A | DONE |
Jim Page
|
|
|
Underground supply flush complete.
|
INSP-Sprinkler Rough-in/Hydro | 8/31/2017 | 9/1/2017 | 9/1/2017 | A | CANC |
Jim Page
|
|
|
Call point of contact (Brad Westbrook ###-####) twice to try and schedule hydro test, received voicemail both times, left a message both times and did not get a call back, inspection request will need to be rescheduled.
|
INSP-Sprinkler Rough-in | 5/25/2017 | 5/26/2017 | 5/26/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 5/17/2017 | 5/18/2017 | 5/18/2017 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for underground complete, current install terminates approximately 60 feet east from 13th street, remaining underground to be installed at a later date, piping installed approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 3/31/2017 | 4/3/2017 | 4/3/2017 | A | PART |
Jim Page
|
|
|
Partial rough to cover for underground supply stub-in complete (Riser section of underground and piping penetrating the footing) Area inspected approved for cover.
|