INSP-Final Inspection | 10/23/2017 | 10/26/2017 | 10/26/2017 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Supervisory signals were verified by Lee at all three buildings today.
|
INSP-Final Inspection | 10/23/2017 | 10/24/2017 | 10/23/2017 | A | CANC |
Jim Page
|
|
|
Rafael Castillo w/ Lea Electric will be onsite for inspection Phone #: ###-#### >> Inspection requested via web by John Siewert Inspection cancelled from web by: John Siewert
|
INSP-Final Inspection | 9/6/2017 | 9/7/2017 | 9/7/2017 | A | PART |
Jim Page
|
|
|
Final fire alarm inspection partially complete, need to verify requirements with the fire alarm plan reviewer for audio/visual notification on the link between the grove hotel, century link arena as well as the district building.
|
INSP-Final Inspection | 9/5/2017 | 9/6/2017 | 9/6/2017 | P | CANC |
Jim Page
|
|
|
Inspection request will be rescheduled due to issues with a NAC panel, this inspection request is cancelled.
|
INSP-Final Inspection | 9/5/2017 | 9/6/2017 | 9/6/2017 | A | CANC |
Jim Page
|
|
|
John Phone #: ###-####
|
INSP-Final Inspection | 8/31/2017 | 9/5/2017 | 9/5/2017 | P | CANC |
Jim Page
|
|
|
Tech - Kc Strykowski
Consolidated with FIR16-00777 and FIR17-00340 Phone #: ###-#### >> Inspection requested via web by John Siewert Inspection cancelled from web by: John Siewert
|
INSP-Final Inspection | 8/15/2017 | 8/16/2017 | 8/16/2017 | P | FAIL |
Troy Cobbley
|
|
|
No city approved plans on site. No inspection performed. As previously stated plans need to be re-submitted and smoke evac zones need tested.
|
INSP-Final Inspection | 7/14/2017 | 7/17/2017 | 7/17/2017 | P | CANC |
Jim Page
|
|
|
Inspection of signals to neighboring buildings. Phone #: ###-#### >> Inspection requested via web by Chris Siewert Inspection cancelled from web by: Chris Siewert
|
INSP-Final Inspection | 6/29/2017 | 6/30/2017 | 6/30/2017 | P | PART |
Troy Cobbley
|
|
|
Temp c of o, phase 3 fire alarm is complete. Fire alarm plans need to be resubmitted for a plan mod due to changes
|
INSP-Final Inspection | 3/29/2017 | 3/30/2017 | 3/30/2017 | A | PART |
Jim Page
|
|
|
Partial final complete for fire alarm system. Area's inspected consist of link between GBAD, Century Link and Boise Center, audio visual devices tested good as well as escalator lobbies on level 1 and level 2. Area's requested for TCO passed/complete (GBAD, Century Link, Boise Center and elevated concourse between Boise Center and west stairwell)
|
INSP-Final Inspection | 3/29/2017 | 3/29/2017 | 3/29/2017 | P | CANC |
Jim Page
|
|
|
Scheduled for 30MAR2017
|