INSP-Final Inspection | 12/4/2017 | 12/4/2017 | 12/4/2017 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection for building 2 passed/complete.
|
INSP-Alarm Testing | 12/1/2017 | 12/4/2017 | 12/4/2017 | A | DONE |
Jim Page
|
|
|
Fire alarm tetsing complete.
|
INSP-Alarm Testing | 11/28/2017 | 11/30/2017 | 11/30/2017 | A | FAIL |
Jim Page
|
|
|
Smoke curtians did not drop when associated smoke detector was activated. Install does not match city approved drawings, contractor needs to resubmit as-built drawings. Levels 1, 2, 3 and 4 are missing audio visual devices, audio visual devices in parking garage are overspaced. FDC bell did not activate with dry system trip.
|
INSP-Final Inspection | 11/28/2017 | 11/28/2017 | 11/28/2017 | P | FAIL |
Jim Page
|
|
|
Fire panel needs to be System is Normal before inspection can be started.
|