INSP-Final Inspection | 6/22/2018 | 6/25/2018 | 6/25/2018 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Contact Ken Orahood - 28-###-#### 30 min prior to Final Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 6/18/2018 | 6/19/2018 | 6/19/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for level 3 witnessed, no pressure loss observed at riser provided gauge.
Contact Ken Orahood -###-#### 30 Min prior to Hydro Insp on 3rd Floor Start please.
thank YOU. Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 6/13/2018 | 6/14/2018 | 6/14/2018 | A | PART |
Jim Page
|
|
|
Hydrostatic test for levels 2, 4 and 5 witnessed, no pressure loss observed at riser provided gauges. Level 3 still needs hydro completed.
Contact Ken Orahood, ###-#### 30 min prior to Hyro Insp start on levels 2, 4, ; 5 please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 6/13/2018 | 6/13/2018 | 6/13/2018 | P | FAIL |
Jim Page
|
|
|
Levels 2, 4 and 5 lost pressure during hydrostatic test.
|
INSP-Sprinkler Rough-in/Hydro | 6/12/2018 | 6/13/2018 | 6/13/2018 | A | PART |
Jim Page
|
|
|
Hydrostatic test for standpipe witnessed, no pressure loss observed at contractor provided gauge.
Contact Ken Orahood ###-#### 30 min prior to Hydro Insp 2nd, 4th, 5th floors and stand pipe start.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 6/12/2018 | 6/12/2018 | 6/12/2018 | P | PART |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping on level 1 witnessed, no pressure loss observed at riser provided gauge. Levels 2, 3, 4, 5 and standpipe to be completed at a later date.
Contact - Ken Orahood - ###-#### 30 min prior to Hydro Insp start on levels 1, 2 4 ; 5 please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 6/8/2018 | 6/11/2018 | 6/11/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above ceiling grid on level 1 complete, approved for cover.
Contact Ken Orahood ###-#### 30 Min prior to RTC 1st Floor Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 6/8/2018 | 6/11/2018 | 6/8/2018 | A | CANC |
Jim Page
|
|
|
Contact - Ken Orahood - 208-297- 9090 30min prior to RTC Insp Start please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in | 5/11/2018 | 5/14/2018 | 5/14/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above hardlids in level 1 east hallway, west conference room and swimming pool area complete, areas inspected approved for cover.
Contact Ken Orahood ###-#### 30 min prior to 1st floor rough in ; hard lid inspection start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 5/7/2018 | 5/8/2018 | 5/8/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above hardlids in main lobby complete, main lobby approved for cover from west of the elevators to the banquet rooms, other rooms off of lobby on level 1 to be inspected at a later date.
Contact Ken Orahood - ###-#### 30 Min Prior to RTC Insp on Lobby Areas please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 4/27/2018 | 4/27/2018 | 4/27/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in hotel guest rooms on level 1 northeast side complete, hotels rooms on level 1 northeast side approved for cover.
|
INSP-Sprinkler Rough-in | 4/11/2018 | 4/12/2018 | 4/12/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in the 28 room on levels 2,3,4 and 5 complete, approved for cover. Rough to cover inspection for overhead fire sprinkler piping in elevator lobbies on levels 2,3,4 and 5 complete, approved for cover.
|
INSP-Supply line flush | 3/29/2018 | 3/29/2018 | 3/29/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overead fire sprinkler piping above hardlids on levels 2, 3, 4 and 5 complete, hardlids approved for cover.
|
INSP-Sprinkler Rough-in | 3/23/2018 | 3/23/2018 | 3/23/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for levels 4 and 5 corridors complete, approved for cover.
|
INSP-Sprinkler Rough-in | 2/22/2018 | 2/22/2018 | 2/22/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located in level 2, 3, and 4 linen/Ice sooms complete as well as added heads on west stairs landings complete, approved for cover.
|
INSP-Sprinkler Rough-in | 1/31/2018 | 2/1/2018 | 2/1/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for rooms on level 5 complete and approved for cover with exception to elevator lobby and room 528, lobby and 528 are not approved for cover.
|
INSP-Sprinkler Rough-in | 12/11/2017 | 12/12/2017 | 12/12/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 4 west of elevator lobby complete, level 4 west of elevator lobby approved for cover.
|
INSP-Sprinkler Rough-in | 12/5/2017 | 12/6/2017 | 12/6/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 5 east of room 511 complete, rooms east of 511 on level 5 approved for cover with exception to room 512, room 512 will be inspected at a later date.
|
INSP-Sprinkler Rough-in | 11/29/2017 | 11/30/2017 | 11/30/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for level 3 west side complete, level 3 west side approved for cover.
|
INSP-Sprinkler Rough-in | 11/14/2017 | 11/17/2017 | 11/17/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 2 complete, level 2 hardlids approved for cover.
|
INSP-Sprinkler Rough-in | 11/7/2017 | 11/8/2017 | 11/8/2017 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete on overhead fire sprinkler piping on level 4, notated city approved plans in jobshack with pink highlighter/red ink areas approved for cover.
|
INSP-Sprinkler Rough-in | 10/20/2017 | 10/23/2017 | 10/23/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located above the sheetrock in corridors (corridors only), east side of elevator lobby on levels 2 and 3 complete, approved for cover.
|
INSP-Sprinkler Rough-in | 10/19/2017 | 10/19/2017 | 10/19/2017 | P | PART |
Jim Page
|
|
|
Rough to cover for overhead fire sprinkler piping on southside of level 4 complete as well as northside level 4 east of the elevator lobby, areas inspected are approved for cover.
|
INSP-Sprinkler Rough-in | 9/29/2017 | 10/2/2017 | 10/2/2017 | A | FAIL |
Jim Page
|
|
|
Installation plans do not match the city approved drawings, installation of fire sprinkler piping needs to match the city approved drawings, cover is not approved for requested area's (Partial corridor cover request on levels 3, 4 and 5). Insulation is installed in area's where cover has not been approved, any fire sprinkler piping that is covered before inspection is completed will have any and all cover material removed for a correct inspection to be performed.
|
INSP-Sprinkler Rough-in | 9/28/2017 | 9/29/2017 | 9/29/2017 | A | CANC |
Jim Page
|
|
|
Contact Hunter Anderson ###-#### 30 min prior to RTC Insp start please. RTC Partial on Hall Ways.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in | 9/19/2017 | 9/20/2017 | 9/20/2017 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located above the pre-rock in the corridor on the level 2 complete, notated the city approved drawings with red ink area's approved for cover. Approved plans for inspections is located in the job shack. Noted that I spoke with the superintendent with Headwaters Construction (Chris Stanton, phone number ###-####) about a temporary standpipe being installed, note number 42 of the building permit fire code review gives the specifics of the temporary standpipe being required.
|
INSP-Sprinkler Rough-in | 9/19/2017 | 9/20/2017 | 9/19/2017 | P | CANC |
Jim Page
|
|
|
Contact Perly Daniel ###-#### 30 min prior to RTC Insp. start please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 9/5/2017 | 9/5/2017 | 9/5/2017 | P | PASS |
Jim Page
|
|
|
Underground supply hydrostatic test complete
|