INSP-Final Inspection | 11/27/2017 | 11/28/2017 | 11/28/2017 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 11/20/2017 | 11/21/2017 | 11/21/2017 | A | PASS |
Troy Cobbley
|
|
|
The exterior canopies have been fire blocked to less than 160 cubic feet. They are ok for cover.
|
INSP-Sprinkler Rough-in/Hydro | 11/20/2017 | 11/20/2017 | 11/20/2017 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test on the dry system passed
|
INSP-Sprinkler Rough-in/Hydro | 11/16/2017 | 11/16/2017 | 11/16/2017 | P | PART |
Troy Cobbley
|
|
|
24 hour air test started at 9:00am with 43psi on guage.
|
INSP-Sprinkler Rough-in/Hydro | 11/15/2017 | 11/16/2017 | 11/15/2017 | A | PASS |
Troy Cobbley
|
|
|
Overhead rough-in and hydro test passed. I need verification that the air compressor is ok and the outside combustible canopies are meet NFPA 13 8.15.7
tom Phone #: ###-####
|
INSP-Supply line flush | 10/9/2017 | 10/10/2017 | 10/10/2017 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed
|