INSP-Final Inspection | 5/29/2018 | 5/30/2018 | 5/30/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
John will be there at 7:00am would like to start as soon as possible. Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 3/19/2018 | 3/19/2018 | 3/19/2018 | P | PASS |
Troy Cobbley
|
|
|
Rough-in and tenting passed. Piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 3/14/2018 | 3/14/2018 | 3/14/2018 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Supply line flush | 3/9/2018 | 3/12/2018 | 3/12/2018 | A | PASS |
Scott Arellano
|
|
|
Flush wItnessed
|
INSP-Sprinkler Rough-in | 2/6/2018 | 2/6/2018 | 2/6/2018 | P | PASS |
Troy Cobbley
|
|
|
The underground supply line is ok for cover.
|