INSP-Final Inspection | 4/24/2018 | 4/25/2018 | 4/25/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in/Hydro | 3/14/2018 | 3/14/2018 | 3/14/2018 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Supply line flush | 3/9/2018 | 3/12/2018 | 3/12/2018 | A | PASS |
Scott Arellano
|
|
|
Flush wItnessed
|
INSP-Sprinkler Rough-in | 2/1/2018 | 2/1/2018 | 2/1/2018 | P | PASS |
Troy Cobbley
|
|
|
Underground Inspection passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 1/19/2018 | 1/19/2018 | 1/19/2018 | P | PASS |
Troy Cobbley
|
|
|
Tenting passed. Piping can be covered
|
INSP-Sprinkler Rough-in | 1/18/2018 | 1/19/2018 | 1/19/2018 | A | FAIL |
Troy Cobbley
|
|
|
Tenting failed again. It still is not attached. A re-inspection fee has been applied.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 1/18/2018 | 1/18/2018 | 1/18/2018 | P | PART |
Troy Cobbley
|
|
|
Rough-in passed but the tenting inspection failed. Piping can not be covered.
|