INSP-Final Inspection | 4/24/2018 | 4/25/2018 | 4/25/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in/Hydro | 3/9/2018 | 3/12/2018 | 3/12/2018 | A | DONE |
Jim Page
|
|
|
Overhead hydrostatic test was witnessed on 9MAR2018, wrong permit was requested on day of inspection request.
|
INSP-Supply line flush | 2/13/2018 | 2/14/2018 | 2/14/2018 | P | DONE |
Jim Page
|
|
|
Undergorund main line flush complete.
|
INSP-Sprinkler Rough-in | 1/10/2018 | 1/11/2018 | 1/11/2018 | A | PASS |
Troy Cobbley
|
|
|
Tenting has been repaired and piping can be covered.
|
INSP-Sprinkler Rough-in | 1/10/2018 | 1/10/2018 | 1/10/2018 | P | PART |
Troy Cobbley
|
|
|
Rough-in passed but the tenting has issues. Piping can not be covered until the tenting has been re-inspected.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 12/14/2017 | 12/14/2017 | 12/14/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|