INSP-Final Inspection | 4/11/2018 | 4/12/2018 | 4/12/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Call 30 minuets prior to arrival Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Final Inspection | 4/10/2018 | 4/11/2018 | 4/11/2018 | A | FAIL |
Troy Cobbley
|
|
|
The sprinkler heads in the second floor mechanical rooms still had the shipping caps on and appeared they may need height adjustment to fit the canopies. The fire riser devices have been tested.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Final Inspection | 4/5/2018 | 4/6/2018 | 4/6/2018 | P | CANC |
Troy Cobbley
|
|
|
Unable to test the sprinkler devices due to fire alarm issues. Contractor needs to verify that the shipping clips have been removed from heads.
|
INSP-Sprinkler Rough-in/Hydro | 3/9/2018 | 3/9/2018 | 3/9/2018 | P | PASS |
Troy Cobbley
|
|
|
overhead hydro test passed
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Supply line flush | 2/13/2018 | 2/14/2018 | 2/14/2018 | P | DONE |
Jim Page
|
|
|
Undergorund main line flush complete.
|
INSP-Sprinkler Rough-in | 12/27/2017 | 12/28/2017 | 12/28/2017 | A | PASS |
Troy Cobbley
|
|
|
Tenting and pipe rough-in passed. Piping can be covered
. Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 12/14/2017 | 12/14/2017 | 12/14/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|