INSP-Final Inspection | 11/6/2017 | 11/7/2017 | 11/7/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Sprinkler Rough-in | 10/26/2017 | 10/27/2017 | 10/27/2017 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations marked with todays date where sprinkler piping is ok for cover.
|
INSP-Sprinkler Rough-in | 10/25/2017 | 10/25/2017 | 10/25/2017 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for level 2, notated city approved plans with green highlighter/red ink areas inspected today and approved for cover.
|
INSP-Sprinkler Rough-in | 10/25/2017 | 10/25/2017 | 10/25/2017 | P | CANC |
Jim Page
|
|
|
Mark Jensen is the contact for this inspection. Thank you. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 10/23/2017 | 10/24/2017 | 10/24/2017 | A | PART |
Jim Page
|
|
|
Partial rough to ocver inspection for level 2, notated the city approved drawings with pink highlighter/red ink areas approved for cover.
|
INSP-Sprinkler Rough-in | 10/18/2017 | 10/19/2017 | 10/19/2017 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for level 2, notated the city approved drawings with yellow highlighter/red ink areas approved for cover.
|
INSP-Sprinkler Rough-in | 10/17/2017 | 10/18/2017 | 10/18/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection complete for level 1, noted the city approved drawings with yellow highlighter/red ink areas approved for cover.
|
INSP-Sprinkler Rough-in | 10/10/2017 | 10/11/2017 | 10/11/2017 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping complete, notated the city approved drawings with pink highlighter and red ink areas approved for cover.
|