INSP-Final Inspection | 3/30/2018 | 4/2/2018 | 4/2/2018 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
RICK FRY Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Final Inspection | 3/29/2018 | 3/30/2018 | 3/30/2018 | A | CANC |
Troy Cobbley
|
|
|
Unable to test the system due to fire alarm interface issues.
RICK FRY Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Final Inspection | 3/14/2018 | 3/15/2018 | 3/15/2018 | A | PART |
Troy Cobbley
|
|
|
I verified the basement wet system tamper switches functioned/reported and I also verifed that the forward flush test passed
Rick Fry Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Final Inspection | 2/28/2018 | 3/1/2018 | 2/28/2018 | A | CANC |
Troy Cobbley
|
|
|
Fire final for 10 AM. Rick Fry Phone #: ###-#### >> Inspection requested via web by Nathan Stenquist Inspection cancelled from web by: Nathan Stenquist
|
INSP-Sprinkler Rough-in/Hydro | 2/5/2018 | 2/6/2018 | 2/6/2018 | A | PASS |
Troy Cobbley
|
|
|
The second floor and pre-action system 200lb hydro tests passed.
|
INSP-Sprinkler Rough-in | 1/31/2018 | 2/1/2018 | 2/1/2018 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test passed. The remaining second floor piping rough-in passed. Piping can be covered. Plan Mod needed showing pipe routing changes for 3" mains and Pre-action system.
|
INSP-Sprinkler Rough-in | 1/31/2018 | 1/31/2018 | 1/31/2018 | P | PART |
Troy Cobbley
|
|
|
24 hour air test started at 9:00am with 51psi on the guage
|
INSP-Sprinkler Rough-in | 1/18/2018 | 1/19/2018 | 1/19/2018 | A | PASS |
Troy Cobbley
|
|
|
See the revised city approved plans for the area on the 2nd floor where the piping can be covered. I noted one missing EQ brace.
Nathan Stenquist. RI INSP for the second floor East side. Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Sprinkler Rough-in/Hydro | 12/13/2017 | 12/13/2017 | 12/13/2017 | P | PASS |
Troy Cobbley
|
|
|
OH hydro for the first floor passed
|
INSP-Sprinkler Rough-in | 12/5/2017 | 12/5/2017 | 12/5/2017 | P | PASS |
Troy Cobbley
|
|
|
The corrections for the piping on the previous inspection have been performed and the piping can be covered.
Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 11/22/2017 | 11/22/2017 | 11/22/2017 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations inspected today where the rough-in was passed. I noted missing siesmic bracing for the branchlines, one missing lateral main bracing and one pendant head overspaced.
Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 11/16/2017 | 11/16/2017 | 11/16/2017 | P | FAIL |
Troy Cobbley
|
|
|
No approved plans on site. No inspection performed
Rick Phone #: ###-####
|