INSP-Final Inspection | 3/9/2018 | 3/14/2018 | 3/14/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Peter Phone #: ###-####
|
INSP-Final Inspection | 11/2/2017 | 11/9/2017 | 11/9/2017 | A | CANC |
Troy Cobbley
|
|
|
Cancel per the tech that was on site.
Natalie Phone #: ###-####
|
INSP-Final Inspection | 10/18/2017 | 10/19/2017 | 10/19/2017 | P | FAIL |
Troy Cobbley
|
|
|
Provide 24 hour back up power as per the review comments for the internet form of communication, relocate the smoke detector to be above the facp, provide the shield wire between the AES and facp, remove the horn/strobe from the lobby, provide as-builts showing the two low air and to water flow switches, provide functional testing of the two low air and two water flow switches, provide document box, provide updated map
Peter - new fire alarm panel Phone #: ###-####
|