INSP-Final Inspection | 7/19/2018 | 7/20/2018 | 7/20/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 7/12/2018 | 7/13/2018 | 7/13/2018 | A | PASS |
Troy Cobbley
|
|
|
The remaining piping can be covered.
|
INSP-Sprinkler Rough-in | 7/12/2018 | 7/12/2018 | 7/12/2018 | P | PASS |
Troy Cobbley
|
|
|
Piping in the Office near the Sterile Corridor can be covered.
Contact Hunter Anderson ###-#### 30 min prior to RTC Insp Start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 7/10/2018 | 7/11/2018 | 7/11/2018 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional areas that are approved for cover.
Contact Hunter Anderson - ###-#### 30 min prior to RTC insp Start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 7/6/2018 | 7/9/2018 | 7/9/2018 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for room locations where overhead piping can be covered.
|
INSP-Sprinkler Rough-in | 5/25/2018 | 5/25/2018 | 5/25/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for fire sprinkler piping located in operating room 1, OR room 1 is notated on the city approved drawings and is approved for cover (total of 4 heads).
Contact Leroy Anderson - ###-#### 30 Min Prior to RTC Insp Start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 5/24/2018 | 5/25/2018 | 5/25/2018 | A | CANC |
Jim Page
|
|
|
Contact Leroy Anderson ###-#### 30 Min Prior to RTC Insp start , please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in | 4/2/2018 | 4/2/2018 | 4/2/2018 | P | PASS |
Troy Cobbley
|
|
|
The fire sprinkler work in the Office, as discussed, is complete.
Contact Jon Olmstead - ###-#### 30 min prior to RTC insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 3/22/2018 | 3/23/2018 | 3/23/2018 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the two rooms where the rough-in has passed and piping can be covered. They are an Office and Vending.
|
INSP-Sprinkler Rough-in | 3/15/2018 | 3/16/2018 | 3/16/2018 | A | PASS |
Troy Cobbley
|
|
|
Work complete in Passage 115
|
INSP-Sprinkler Rough-in | 3/14/2018 | 3/15/2018 | 3/15/2018 | A | FAIL |
Troy Cobbley
|
|
|
Ceiling tile has not been installed in Passage 115
Contact Jon Olmstead ###-#### 30 min prior to RTC Start please Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 3/13/2018 | 3/14/2018 | 3/14/2018 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for location where the piping can be covered in Passage 115.
Contact Jon Olmstead - ###-#### 30 min prior to Rough-In start please Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 3/12/2018 | 3/13/2018 | 3/13/2018 | A | FAIL |
Troy Cobbley
|
|
|
No city approved drawings on site. No inspection performed. I also noted missing fire proofing.
|