INSP-Final Inspection | 1/30/2018 | 1/31/2018 | 2/1/2018 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 1/24/2018 | 1/26/2018 | 1/26/2018 | A | FAIL |
Troy Cobbley
|
|
|
Contact the plan reviewer for guidance on wether a plan modification is needed or if as-builts will suffice.The one line riser does not match actual points and descriptions such as dry system pressure switch, AES instead of phone lines....ect. Also per dicussion with on site electrician, hvac and general contractor not all of the duct smoke detectors are functional I stated that all devices, as shown on the plans, need to be installed/cunctional/tested or plans will need to be modified to delete the devices. The deleted devices will require a separate permit when installed prior to an occupancy approval for the individual tenants. Today we tested all devices except the flow switch for system #2 and the duct smoke detectors.
This is for Belmont Core Phone #: ###-#### Inspection requested via web by Ken Webster
|