INSP-Final Inspection | 1/25/2018 | 1/26/2018 | 1/26/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 1/5/2018 | 1/5/2018 | 1/5/2018 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Correctlons have been made at the mezzanine
|
INSP-Sprinkler Rough-in | 12/20/2017 | 12/21/2017 | 12/21/2017 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for the mezzanine in the back area. I had to fail it due to heads overspaced from the exterior wall, pipe size does not match plans and possible need for branchline restraints.
Contact Scott Powada - ###-####
|
INSP-Sprinkler Rough-in | 12/12/2017 | 12/13/2017 | 12/13/2017 | A | PASS |
Troy Cobbley
|
|
|
The Sales Floor area, as marked on the plans, is ok for cover
Contact Scott Powada ###-#### 30 min prior to TRC Insp Start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|