INSP-Final Inspection | 12/22/2017 | 12/26/2017 | 12/26/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete
|
INSP-Sprinkler Rough-in | 12/8/2017 | 12/8/2017 | 12/8/2017 | P | PASS |
Jim Page
|
|
|
Rouh to cover inspection for area of work complete, approved for cover. In tenant space there are two different types of heads in the same area, Viking Standard response GB 155 degree and Reliable Model G heads, model G heads need to be changed to glass bulb Viking heads. Head change will be verified at final inspection.
|
INSP-Final Inspection | 12/8/2017 | 12/8/2017 | 12/8/2017 | P | CANC |
Jim Page
|
|
|
Tenant space not ready for final inspection, this inspection request is going to be changed to a rough in inspection.
|