INSP-Final Inspection | 5/7/2018 | 5/7/2018 | 5/7/2018 | P | PASS |
Jim Page
|
|
|
Fire sprinkler monitoring has been interfaced with the newly installed fire alarm system, this permit is finaled.
|
INSP-Final Inspection | 2/9/2018 | 2/9/2018 | 2/9/2018 | P | CANC |
Jim Page
|
|
|
Wrong permit request generated, this inspection request is cancelled.
|
INSP-Final Inspection | 1/11/2018 | 1/12/2018 | 1/12/2018 | A | PART |
Troy Cobbley
|
|
|
Only item tested was, per Colton and the scope of work, is the main flow switch. The flow switch I tested was located at the main riser in the basement. I noticed that all of the tamper switches on this riser in the basement had been lock/chained open. I can't final until all devices have been connected/tested.
temp- Colton Phone #: ###-####
|