INSP-Final Inspection | 7/12/2018 | 7/12/2018 | 7/12/2018 | P | PASS |
Jim Page
|
|
|
Final inspection for undergorund supply complete.
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2018 | 7/12/2018 | 7/12/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for underground supply witnessed, no pressure loss observed at riser provided gauge.
underground hydro Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Supply line flush | 7/11/2018 | 7/12/2018 | 7/12/2018 | A | DONE |
Jim Page
|
|
|
Undergorund main line flush complete.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Supply line flush | 6/27/2018 | 6/28/2018 | 6/28/2018 | A | DONE |
Jim Page
|
|
|
Underground supply flush complete.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 4/12/2018 | 4/12/2018 | 4/12/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|
INSP-Final Inspection | 4/11/2018 | 4/12/2018 | 4/12/2018 | A | CANC |
Jim Page
|
|
|
Inspection request is for a rough in, not a final inspection, this request is cancelled.
|
INSP-Sprinkler Rough-in | 3/7/2018 | 3/7/2018 | 3/7/2018 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection for underground supply complete, IBR and small section past footing approved for cover, remaining underground to be installed at a later date.
|