INSP-Final Inspection | 6/27/2018 | 6/28/2018 | 6/28/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Rand Phone #: ###-####
|
INSP-Final Inspection | 6/25/2018 | 6/26/2018 | 6/26/2018 | A | FAIL |
Troy Cobbley
|
|
|
Need Lee to approve as-builts when received.
Rand Phone #: ###-####
|
INSP-Final Inspection | 6/22/2018 | 6/25/2018 | 6/26/2018 | A | FAIL |
Troy Cobbley
|
|
|
See Lee's inspection notes for corrections needed.
Rand Phone #: ###-####
|
INSP-Final Inspection | 6/22/2018 | 6/25/2018 | 6/25/2018 | P | CANC |
Troy Cobbley
|
|
|
Rand Phone #: ###-####
|
INSP-Alarm Testing | 6/21/2018 | 6/22/2018 | 6/22/2018 | A | DONE |
Troy Cobbley
|
|
|
Today we finished up the marked corrections on the 4th floor including dampers but no elevator control. But programming has been changed so that the room detectors/sounder bases activate upon another rooms supervisory alarm. This needs to be corrected and devices retested. We went to the 3rd and 2nd floors and found that the room detector/sounder bases are also incorrect. So I inspected the fire dampers on the 3rd and 2nd floors. The detectors will need to be spot check for functionality on the 4th floor and 100% checks on the remaining floors. No elevator has been tested. The strobes in the Handicap rooms still do not have the weather proof boxes installed. The dampers at the top of the elevator shafts functioned.
Rand Phone #: ###-####
|
INSP-Final Inspection | 6/20/2018 | 6/21/2018 | 6/21/2018 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for the 4th floor. See the city approved plans for all devices tested and the corrections needed such as Room Number/device address corrections. The general alarm silence feature does not function yet. The fire smoke dampers are not accessible for inspection.
Randy Phone #: ###-####
|
INSP-Alarm Testing | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | DONE |
Troy Cobbley
|
|
|
The FACP, phone lines and batteries have been verified. The interconnection with the fie sprinkler devices have been verified. Alarm points for devices tested have been verified.
Tom Phone #: ###-####
|
INSP-Alarm Testing | 6/14/2018 | 6/14/2018 | 6/14/2018 | P | FAIL |
Troy Cobbley
|
|
|
Plan mods are needed showing the changes which include addresses and fire sprinkler device layout. I tried testing today but when we started there were 79 troubles on the panel. When test for sprinkler alarms the panel started functioning incorrectly. I ended the inspection. Project is not ready for inspection.
Rand Phone #: ###-####
|
INSP-Sprinkler Rough-in | 6/7/2018 | 6/8/2018 | 6/8/2018 | P | CANC |
Troy Cobbley
|
|
|
Per Rand this will be rescheduled for monday or tuesday.
Rand Phone #: ###-####
|