Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR18-00173
StatusFinaled
Name TRIBAL FIRE SYSTEMS
Site Address 8000 S FEDERAL WAY
Project NameMicron Building 51 System20-13
Customer Number 
ePlanReviewYes
Description
[Micron Building 51 - System 20-13 - C24074]
The fire sprinkler scope of work consists of part of the level 20. The system is a small side feed dry system for the dock. The owner has confirmed there will be no chemical storage.

• The underground is under permit FIR16-00701
• See addendum for graphic scope of work
[BLD16-03440]
For the construction of a new one story building with a basement for a fabrication and R&D facility to include related site work. The building includes a 157,037 sq. ft. basement, a 170,997 sq. ft. first story and a 33,638 sq. ft. equipment platform. This building is fully fire sprinklered and alarmed for H occupancy. CDM

Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.

• There are a number of AMM on this project. However, none affects this fire protection system.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/23/20184/24/20184/24/2018APASS
DetailsJim Page
Final fire sprinkler inspection for dry system complete.
INSP-Sprinkler Rough-in/Hydro4/24/20184/24/20184/24/2018PDONE
DetailsJim Page
24 hour air test witnessed, no pressure loss observed at dry pipe valve provided gauge.
INSP-Sprinkler Rough-in4/20/20184/23/20184/23/2018APART
DetailsJim Page
24 hr air test started at 1230PM @ 40PSI
INSP-Final Inspection4/17/20184/20/20184/20/2018AFAIL
DetailsJim Page
Final inspection will not be performed until completion of 24 hour air test.
INSP-Sprinkler Rough-in4/10/20184/10/20184/10/2018PPASS
DetailsJim Page
Rough in inspection for area of work complete.
INSP-Sprinkler Rough-in/Hydro4/9/20184/10/20184/10/2018PDONE
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.