INSP-Final Inspection | 3/11/2019 | 3/11/2019 | 3/11/2019 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, as-builts have been approved. Final inspection for AES complete.
bill Phone #: ###-####
|
INSP-Final Inspection | 3/8/2019 | 3/8/2019 | 3/8/2019 | P | CANC |
Jim Page
|
|
|
Does not appear as-builts have been reviewed per activities under this permit. After discussion with point of contact, inspection request will be rescheduled for a later date, this request is cancelled per conversation with POC.
Bill Phone #: ###-####
|
INSP-Final Inspection | 3/6/2019 | 3/6/2019 | 3/6/2019 | P | FAIL |
Troy Cobbley
|
|
|
Alarmco's as-builts showed wrong panel. tested signal. panel trouble relay does not latch and resets when silenced. signals report. To final permit ad-builts needed.
call ahead // bill Phone #: ###-####
|
INSP-Final Inspection | 3/5/2019 | 3/5/2019 | 3/5/2019 | P | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact, will be rescheduled for a later date.
Bill Phone #: ###-####
|