INSP-Final Inspection | 1/22/2019 | 1/23/2019 | 1/23/2019 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection for area of work complete.
Brian Phone #: ###-####
|
INSP-Final Inspection | 5/10/2018 | 5/11/2018 | 5/11/2018 | A | CANC |
Troy Cobbley
|
|
|
Simplex has not performed their portion of work per Brian Anderson. The system is not ready for testing
Brian Phone #: ###-####
|
INSP-Final Inspection | 4/5/2018 | 4/6/2018 | 4/6/2018 | A | PART |
Troy Cobbley
|
|
|
Phase one (CT#2 Room/Control Room) fire alarm work is complete except there is a audible sync issue and it appears that a visual sync issue. The sync issues will need to be addressed prior to a final sign off.