INSP-Final Inspection | 11/8/2018 | 11/9/2018 | 11/9/2018 | A | PASS |
Jim Page
|
|
|
Final inspection for scope of work complete.
Please call Troy with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Sprinkler Rough-in/Hydro | 11/9/2018 | 11/9/2018 | 11/9/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for underground supply re-route witnessed, no pressure loss observed.
|
INSP-Sprinkler Rough-in/Hydro | 11/5/2018 | 11/6/2018 | 11/6/2018 | P | CANC |
Troy Cobbley
|
|
|
UG Hydro for 8" service. Please call Troy With time frame. Phone #: ###-#### >> Inspection requested via web by Jeff Packham Inspection cancelled from web by: Jeff Packham
|
INSP-Sprinkler Rough-in/Hydro | 11/5/2018 | 11/5/2018 | 11/5/2018 | P | CANC |
Troy Cobbley
|
|
|
Scheduled for the wrong day.
Hydro Test for 8" UG.
Please call Troy with time frame. Thanks Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Sprinkler Rough-in/Hydro | 11/2/2018 | 11/5/2018 | 11/5/2018 | A | CANC |
Jim Page
|
|
|
UG Cover/Hydro Troy Phone #: ###-#### >> Inspection requested via web by Nathan Stenquist Inspection cancelled from web by: Nathan Stenquist
|
INSP-Supply line flush | 10/22/2018 | 10/22/2018 | 10/22/2018 | P | DONE |
Jim Page
|
|
|
Undergound main line flush witnessed and is complete.
|
INSP-Sprinkler Rough-in/Hydro | 10/19/2018 | 10/22/2018 | 10/22/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for ocver.
UG Hydro Troy Nelson Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Conference | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | DONE |
Jim Page
|
|
|
Conference for undergorund supply complete.
|
INSP-Sprinkler Rough-in | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | CANC |
Jim Page
|
|
|
Reuqest was for conference, this request is canceeld.
UG Cover Troy Nelson Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|