[Sherman Hollow 20-1]
The fire sprinkler scope of work consists of a new single family two level home. The system is designed as a passive purge system. The system utilizes CPVC piping and residential type sprinklers.

[BLD18-03105]
Permit for the construction of a new 2493 sq. ft., two story (first story 1260 sq. ft., second story 1233 sq. ft.) single family dwelling with 4 bedrooms, 3 bathrooms, approximately 139 sq. ft. of covered patio/porch and a 621 sq. ft. attached garage per the approved plans and any notations. R-1B zoning and setbacks per planning.

Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.

• There are no AMM at this time
Plan Mod 2/5/2019 Approved **MAS**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/9/201912/10/201912/10/2019APASS
DetailsJim Page
Final fire sprinkler inspection is complete.

Please call before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
INSP-Sprinkler Rough-in5/23/20195/23/20195/23/2019APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping complete, changes were required outside of what was shown on the city approved drawings, as-builts will be submitted showing changes. Cover is approved at the contractors discretion, if changes need to be made due to as-builts not meeting requirements then cover material will need to be removed for corrections. Plastic sheeting used for tenting, all tenting in place at time of inspection.
INSP-Sprinkler Rough-in/Hydro5/22/20195/23/20195/23/2019ADONE
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping witnessed at 140 psi (static pressure is required at a minimum, the hydro was completed with pressure above static city pressure), no pressure loss was observed.

Rough/hydro and tenting inspection. Please call James before heading out.

Thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello