INSP-Final Inspection | 12/9/2019 | 12/10/2019 | 12/10/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete.
Please call before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 5/23/2019 | 5/23/2019 | 5/23/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, changes were required outside of what was shown on the city approved drawings, as-builts will be submitted showing changes. Cover is approved at the contractors discretion, if changes need to be made due to as-builts not meeting requirements then cover material will need to be removed for corrections. Plastic sheeting used for tenting, all tenting in place at time of inspection.
|
INSP-Sprinkler Rough-in/Hydro | 5/22/2019 | 5/23/2019 | 5/23/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed at 140 psi (static pressure is required at a minimum, the hydro was completed with pressure above static city pressure), no pressure loss was observed.
Rough/hydro and tenting inspection. Please call James before heading out.
Thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|