INSP-Final Inspection | 1/16/2019 | 1/17/2019 | 1/17/2019 | P | PASS |
Jim Page
|
|
|
Final fire alarm inspection for area of work complete.
This inspection needs to be between 4 and 5pm. The inspection is being coordinated with the Boise Center on the Grove as well as sprinkler, electrician and us. Our technician that will be at the inspection is Peter Naumov. His number is ###-#### Phone #: ###-#### Inspection requested via web by Cheyenne Zumstein
|
INSP-Final Inspection | 1/8/2019 | 1/10/2019 | 1/10/2019 | P | FAIL |
Jim Page
|
|
|
Resubmit plans showing new NAC panel. Need to meet sound requirements in discussed areas. Provide calculations for 3rd circuit used.
This inspection is being requested to be done after 1:30pm as they are having to coordinate with the Boise Center on the Grove. Crane Alarm''s technician for this final is Eric Nelson ###-#### Phone #: ###-#### Inspection requested via web by Cheyenne Zumstein
|