Information based on query as of Saturday, June 22, 2024.
Permit Information
Permit NumberFIR18-00815
StatusFinaled
Name PROTEX
Site Address 3536 W HILL RD
Project NameHillside Junior High TI
Customer Number 
ePlanReviewYes
Description
Upgrade existing fire alarm system to Voice. This work is not associated with a building permit.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/10/20195/10/20195/10/2019PPASS
DetailsTroy Cobbley
Permit finaled. Previous corrections addressed.

Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
INSP-Final Inspection5/9/20195/9/20195/9/2019PFAIL
DetailsMark Scharfen
Checked prints with cut sheets. Tested notification, gym circuit worked. On testing duct detectors, none of the fans shut down. Wires were disconnected on the fire alarm interface in the roof top unit. Protex is to fix the issue with shutdown and verify all units shut down. Next test will need to test all 5 duct detectors for shurdown.

Contact is Dirk. Phone #: ###-#### >> Inspection requested via web by Morgan Ahten
INSP-Final Inspection5/6/20195/7/20195/7/2019AFAIL
DetailsMark Scharfen
Gym speaker circuit was not working (disabled in programming per dirk). Unable to get HVAC units running for testing shutdown. Asbuilds do not match what is installed. Gym has 115CD strobes but prints and load sheets show 110CD. Current rating doesn't match cut sheet for alarm current draw. Plans will need to be submitted as a plan mod prior to next inspection. Next inspection will have a reinspection fee.

Contact is Dirk. Phone #: ###-#### >> Inspection requested via web by Morgan Ahten
INSP-Final Inspection4/29/20194/29/20194/29/2019PFAIL
DetailsMark Scharfen
No Building map at panel or remote command center. No lift to test duct detectors or check cd on strobes in gym. will reschedule.

Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
INSP-Final Inspection3/21/20193/22/20193/22/2019PPART
DetailsJim Page
Final fire alarm inspection for phase 1 TCO complete.

Contact is Dan. Phone #: ###-#### Inspection requested via web by Morgan Ahten
INSP-Final Inspection3/20/20193/21/20193/21/2019PFAIL
DetailsJim Page
Pull station in riser room mounted to low. Provide city approved drawings and small documents, no city approved drawings on site. Provide document cabinet at fire panel. Provide map showing initiating devices. Only item tested is the commercial hood interface, hood suppression system reports to panel.

Partial Final for cafeteria and commons. Contact is Dan. Phone #: ###-#### Inspection requested via web by Morgan Ahten