Permit Information
Permit NumberFIR18-00882
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 2800 S MAPLE GROVE RD
Project NameMAPLE GROVE ELEM. GYM & CLASS
Customer Number 
ePlanReviewYes
Description
[Maple Grove Elementary Gym Addition]
The fire sprinkler scope of work consists of installing a complete sprinkler system in the new addition. Leave a cap for future expansion of the sprinkler system to the existing building. The system consists of two trees and a side feed layout. The 6” underground supplies a 4” backflow preventer and 4” riser.

• The underground piping was installed under permit FIR18-00614.

[BLD18-00776]
Special inspections are required per the attached form 310. This project consists of constructing a 12,003 sq. ft. addition to an existing 45,000 sq. ft. elementary school. The addition includes a gymnasium and support spaces, 5 new classrooms, minor site upgrades, and minor utility work per the approved plans. The new building will be fully fire sprinklered and alarmed. The existing 45,000 sq. ft. building is considered a separate building and will be fire sprinklered per the attached upgrade agreement by December of 2019. The walls separating the new and existing building are to be constructed per the attached code modification. CDM

Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.

• There is one AMM. (See addendum.)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/15/20198/15/20198/15/2019APASS
DetailsTroy Cobbley
Permit finaled

Please call Rick with time frame
Phone #: ###-#### Inspection requested via web by Jeff Packham
INSP-Final Inspection8/9/20198/9/20198/9/2019PCANC
DetailsJim Page
Cancelled per conversation with point of contact, fire alarm not ready.

please call jeff with time frame Phone #: ###-#### Inspection requested via web by Jeff Packham
INSP-Sprinkler Rough-in/Hydro6/3/20196/3/20196/3/2019PPASS
DetailsTroy Cobbley
The overhead hydro passed with no visible loss at the guage.

Mike Phone #: ###-####
INSP-Sprinkler Rough-in5/2/20195/3/20195/3/2019APASS
DetailsTroy Cobbley
Rough-in passed and piping is ok for cover for both of the entry lobbys from the gym

Rick Phone #: ###-####
INSP-Sprinkler Rough-in3/27/20193/28/20193/28/2019APASS
DetailsTroy Cobbley
overhead rough-in passed. Piping above hardlids can be covered. The wood above the ceiling in the west end corridor will need to be addessed. Riser is not built yet. // Rick Phone #: ###-####
INSP-Sprinkler Rough-in12/17/201812/18/201812/18/2018PPASS
DetailsTroy Cobbley
Underground piping is ok for cover.

TROY NELSON IS OUR CONTACT UNDERGROUND COVER INSPECTION Phone #: ###-#### Inspection requested via web by Brad Bettencourt